NEW YONGSAN YOUTH ACTIVITY CENTER
Construction included an addition to the existing Yongsan Youth Activity Center. Adding a large multi purpose room, exercise room, office space, storage, restrooms, lobby , site improvements and fire protection system.
Est Construction Cost $2,650,000 |
Actual Cost $2,390,064 |
Schedule Completion 15 Nov 1997 |
Actual Completion 15 Dec 1997 |
Contracting Officer Far East District, COE Seoul, Korea |
CFSC Project Manager Kevin Orton |
A/E Design Firm TJDavis/JI Seoul, Korea |
Contractor Song Bo Const.Ind,Co Seoul, Korea |
Summary: The Yongsan Youth Facility Center supports 2,500 youths living in the community. The center will now be able to offer the wider variety of programs for the community teens and youths on a year round basis.
|