DUGWAY P. G. GOLF MAINTENANCE FACILITY
This project constructed a new 2,700sf Golf Course Maintenance Facility including maintenance bays with drive-thru capability, cart staging area, equipment storage and wash-down area, a self contained water bio-recycling system, break room, and bath and shower facilities. The new building is sited adjacent to an existing storage building creating an efficient new maintenance facility.
Actual Cost $365,000.00 |
Schedule Completion December 2002 |
Actual Completion November 2002 |
Project Manager CFSC: Joe Bloomer |
Contracting Officer CFSC: Todd Lennox |
D/B Contractor The Haskell Company |
|