The PPV Process
- INSTALLATION INITIATES PROJECT
- Letter of Intent (GC thru Region/IMA)
- Local Congressional & Community Support Letters (GC, DCA, PAO)
- Project Submission Information to CFSC (DCA,DPW) w/ copy of ROA.
- Original ROA (DPW thru Region & IMA to ACSIM)
- Real Estate Appraisal (CFSC & COE) once ROA leaves installation
- PROJECT APPROVALS (24 Weeks)
- ACSIM submits ROA to OASA(I&E) for DOA
- CFSC submits request to OASA(M&RA) for approval to proceed with project
- After DOA and project approval received CFSC submit project to OSD for Congressional Committee approval with NAF Major Construction Program submissions
- Industry Competition
- Issue Request for Proposal (RFP)
- Pre-Proposal conference at Installation
- Source Selection Evaluation Board
- Issue Conditional Notice of Award
- FINALIZE DEVELOPMENT AGREEMENT (14 Weeks)
- Business Plan Development and Review (Inst/Developer/CFSC)
- Notify OASA(M&RA) of approved business plan and secure approval to award thru OSD
- Two Week Contract Award Notification to Congressional Committees
- AWARD CONTRACT & EXECUTE LEASE (2 Weeks)
- Appoint COR
- Finalize Lease (USACE/Developer)
- Finalize MOA w/Installation
|
|